Client: Hospital

Location: South Africa

Services: Virtual Pipeline

Large traffic issues caused a long delay in the delivery of the CNG Transport module to the South African hospital. Site operations set the trailer changeover pressure at a standard 10 bar (144 psi). The operators at the mother station remotely lowered the shutdown pressure via Scada to 3 bar (44 psi) so the decant panel continued to operate, as the trailer was now only minutes away. The trailer decanted to 4 bar (58psi) with a flow rate of approximately 440 scfm using the Bison Decanting system. The new trailer was connected and there was no delay in the supply of gas to the site.